SSCHED_UPDATE_SUMMARY_BY_TASK

Syntax

SSCHED_UPDATE_SUMMARY_INTERVAL=integer

Description

Used by Platform Session Scheduler (ssched).

Update the Session Scheduler task summary via bpost after the specified number of tasks finish. Specify a value greater than or equal to zero (0).

If both SSCHED_UPDATE_SUMMARY_INTERVAL and SSCHED_UPDATE_SUMMARY_BY_TASK are set to zero (0), bpost is not run.

Valid values

Specify a positive integer between 0 and 2147483645

Default

0

See also

SSCHED_UPDATE_SUMMARY_INTERVAL